Construction Updates

Stages in progress

Eucalyptus Release - Stage 1

Lots 101 – 122

Anticipated Registration – November 2024

Anticipated Settlement – December 2024

0%
Bulk Earth Works100%
Civil Works100%
Valuation AccessJuly
Electrical & Communications Works 95%
Landscaping95%

Boronia Release - Stage 2

Lots 201 – 217

Anticipated Registration – November 2024

Anticipated Settlement –  December 2024

0%
Bulk Earth Works100%
Civil Works100%
Valuation AccessJuly
Electrical & Communications Works95%
Landscaping95%

Bottlebrush Release - Stage 8

Lots 801 – 812

Anticipated Registration –  November 2024

Anticipated Settlement –  December 2024

0%
Bulk Earth Works100%
Civil Works100%
Valuation AccessJuly
Electrical & Communications Works95%
Landscaping95%

Melaleuca Release - Stage 3

Lots 301 – 319

Anticipated Registration –  November 2025

Anticipated Settlement –  December 2025

Anticipated Valuation Access – Late September 2025

Anticipated Soil Test Access –  Late September 2025

0%
Planning100%
Civil Works33%
Electrical & Communication Works0%
Landscaping0%

Protea Release - Stage 4

Lots 401 – 439

Anticipated Registration –  November 2025

Anticipated Settlement –  December 2025

Anticipated Valuation Access – Late September 2025

Anticipated Soil Test Access – Late September 2025

0%
Planning100%
Civil Works33%
Electrical & Communications Works0%
Landscaping0%

Completed stages

Eucalyptus Release - Stage 1

Lots 101 – 122

Titles Registered – December 2024

Boronia Release - Stage 2​

Lots 201 – 217

Titles Registered – December 2024

Bottlebrush Release - Stage 8

Lots 801 – 812

Titles Registered – December 2024